Ventris Company found that one of its manufacturing cells had actual cycle time of 15 minutes per

Question:

Ventris Company found that one of its manufacturing cells had actual cycle time of 15 minutes per unit. The theoretical cycle time for this cell was 9 minutes per unit.

Required:

1. Calculate the amount of processing time per unit and the amount of nonprocessing time per unit.

2. Calculate the MCE.