Question: WCM Builders enters into a contract to build a shopping mall in 2016 for $6,000,000. Completion of the mall is expected to take 2 years
WCM Builders enters into a contract to build a shopping mall in 2016 for $6,000,000. Completion of the mall is expected to take 2 years and cost WCM $3,600,000. Upon signing the contract, WCM receives $600,000. During 2016, WCM incurs costs of $1,200,000 and receives a $1,000,000 progress payment. WCM's forewoman estimates that the job is 50% complete at the end of 2016. How much income must WCM recognize in 2016 from work done on the mall?
Step by Step Solution
★★★★★
3.41 Rating (164 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
WCM must use the percentageofcompleted contract method to recognize incom... View full answer