You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Draw a

Question:

You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Draw a project network given the information below. Complete the forward and backward pass, compute activity slack, and identify the critical path.

How long will this project take? How sensitive is the network schedule? Calculate the free slack and total slack for all noncritical activities.

ID Description Predecessor Time (days) A Systems design None Subsystem A design A 1 C Subsystem B design 2 Subsystem C d
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management The Managerial Process

ISBN: 978-1259666094

7th edition

Authors: Erik W. Larson, Clifford F. Gray

Question Posted: