You have signed a contract to build a garage for the Simpsons. You will receive a $500

Question:

You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 7 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 7 working days.

Draw a project network given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project?

ID Description Time (days) Predecessor Prepare site A None 2 Pour foundation B B 3 Erect frame 4 Roof D 4 Windows 1 Door
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management The Managerial Process

ISBN: 978-1259666094

7th edition

Authors: Erik W. Larson, Clifford F. Gray

Question Posted: