a. Purchase price of four acres of land .......................................... $209,000
b. Additional dirt and earth moving ................................................... 8,500
c. Fence around the boundary of the property ..................................... 16,200
d. Attorney fee for title search on tile land .......................................... 1,800
e. Unpaid property taxes on tile land to be paid by Zenith ........................ 6,100
f. Company signs at the front of the property ...................................... 4,100
g. Building permit for the building ................................................... 3,200
h. Architect's fee for the design of the building .................................. 23,000
i. Labor to construct the building .................................................. 357,900
J. Materials used to construct the building ....................................... 306,000
k. Landscaping .......................................................................... 6,200
I. Parking lot and concrete walks ................................................... 28,600
m. Lights for the parking lot and walkways .......................................10,200
n. Salary of construction supervisor (80% to building;
20% to parking lot and concrete walks) ........................................... 50,000
a. Furniture for the building ....................................................... 107,100
p. Transportation and installation of furniture ..................................... 2,100
Zenith Manufacturing depreciates buildings over 35 years, land improvements over 15 years, and furniture over 12 years, all on a straight-line basis with zero residual value.
Requirements
1. Set up columns for Land, Land Improvements, Building, and Furniture. Show how to account for each cost by listing the cost under the correct account. Determine the total cost of each asset.
2. All construction was complete and the assets were placed in service on July 1. Record partial-year depreciation for the year ended December 31. Round intermediate calculations to the nearest cent and final answers to the nearest whole dollar.