A project being analyzed by PERT has 60 activities, 13 of which are on the critical path.
Fantastic news! We've Found the answer you've been seeking!
Question:
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, the probability that the project will take 224 days or more to complete is what?