Question: A construction project has the following network and activity times: a. Make a forward pass and a backward pass on the activity times. b. Find

A construction project has the following network and activity times:

A construction project has the following network and activity times:a.

a. Make a forward pass and a backward pass on the activity times.
b. Find the slack for each activity.
c. Prepare a Gantt chart for this project.
d. Activity D will be delayed by one day. What effect will this have on the project?

4 0 Start End 7

Step by Step Solution

3.49 Rating (172 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Forward and Backward pass Activity ES EF LS LF A 0 2 0 2 B 2 7 5 10 C 2 5 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

555-B-M-L-S-C-M (3620).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!