Question: The following activities are required in starting up a new plant: a. Draw a network for this project. b. Make a forward and backward pass
The following activities are required in starting up a new plant:
.png)
a. Draw a network for this project.
b. Make a forward and backward pass to deter mine ES, LS, EF, and LF.
c. Calculate slack.
d. Prepare a Gantt chart for this project.
Immediate Predecessor Activity Time Activity C, D E, C, D
Step by Step Solution
3.56 Rating (174 Votes )
There are 3 Steps involved in it
a Network b Activity ES EF LS LF a 0 3 2 5 b 0 2 0 2 c 3 5 5 7 d 2 7 2 7 e ... View full answer