A construction project requires five major pieces of work to be completed which are independent. These five

Question:

A construction project requires five major pieces of work to be completed which are independent. These five paths have variances as given in Table. Determine the probability that the project will be completed within:

(a) 18 weeks.

(b) 16 weeks.

(c) 13 weeks.