Considering the critical path alone for the project n Table, calculate the activity variances and the total

Question:

Considering the critical path alone for the project n Table, calculate the activity variances and the total variance of the critical path. From this, calculate the standard deviation. Determine the probability of the project being completed within the following times:
(a) 30 days.
(b) 40 days.
(c) 42days.