Question:

A firm is going to finance a new project 100 percent with debt, through a new bond issue. Since the firm is using only debt to finance the project, the NPV of the project should be calculated using the cost of debt as the discount rate. Is this statement true, false, or uncertain? Explain.

Cost Of Debt
The cost of debt is the effective interest rate a company pays on its debts. It’s the cost of debt, such as bonds and loans, among others. The cost of debt often refers to before-tax cost of debt, which is the company's cost of debt before taking...