Question: A particular load has a pf of 0.8 lagging. The power delivered to the load is 40kW from a 220-V rms 60-Hz line, what value
A particular load has a pf of 0.8 lagging. The power delivered to the load is 40kW from a 220-V rms 60-Hz line, what value of capacitance placed in parallel with the load will raise the pf to 0.9 lagging?
Step by Step Solution
3.40 Rating (175 Votes )
There are 3 Steps involved in it
Sold Qold Sold 50k VA Dold vai 08 3687 Sold 50 3687 KVA ... View full answer