Question: A project consists of the following tasks, with task times in weeks. Use the data provided to identify the projects critical path. ask PrecedingL ask

A project consists of the following tasks, with task times in weeks. Use the data provided to identify the project€™s critical path.

A project consists of the following tasks, with task times

ask PrecedingL ask Preceding Tasks A None 8 910 B None 5 912 CA DIB 8 1419 E C, D FIE 10 1418 GIF 6 10 15