A project has a task with the following task time estimates: Pessimistic completion time = 18 weeks

Question:

A project has a task with the following task time estimates:
Pessimistic completion time = 18 weeks
Most likely completion time = 15 weeks
Optimistic completion time = 7 weeks.
What is the estimated completion time for the task?
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managing Supply Chain and Operations An Integrative Approach

ISBN: 978-0132832403

1st edition

Authors: Thomas Foster, Scott E. Sampson, Cynthia Wallin, Scott W Webb

Question Posted: