Assume a project will result in benefits of $1 trillion in 500 years by avoiding an environmental
Question:
Assume a project will result in benefits of $1 trillion in 500 years by avoiding an environmental disaster that otherwise would occur at that time.
a. Compute the present value of these benefits using a time-constant discount rate of 3.5.
b. Compute the present value of these benefits using the following time-declining discount rate schedule: 3.5 percent, years 1-50; 2.5 percent, years, 51-100; 1.5 percent, years 101-200; 0.5 percent, years 201-300; and 0 percent thereafter.
Discount RateDepending upon the context, the discount rate has two different definitions and usages. First, the discount rate refers to the interest rate charged to the commercial banks and other financial institutions for the loans they take from the Federal...
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Cost Benefit Analysis Concepts and Practice
ISBN: 978-0137002696
4th edition
Authors: Anthony Boardman, David Greenberg, Aidan Vining, David Weimer
Question Posted: