Assume the customer has ordered 50 units of each product. Well use a process batch of 100

Question:

Assume the customer has ordered 50 units of each product. We€™ll use a process batch of 100 units and a transfer batch of one. Make a Gantt chart for each machine to show us how quickly you can ship the customer€™s order. Earliest shipment gets 5 extra points on the final exam.€

Assume the customer has ordered 50 units of each product.

€œAnd do you have the answer to Problem 6, Pete?€ asked Professor Grasso.
€œYes sir, I have the answer according to the textbook, but I€™m not sure I get it,€ replied Pete.
€œYou don€™t understand how to get the solution?€ €œOh, I understand the numbers, but I don€™t know what they€™re good for. Where I work, nobody ever €˜sequences€™ anything. You don€™t have time to calculate things like slack and critical ratio. You do what€™s next in line or on top of the stack, unless you see a red tag on something that needs to be rushed through. Or maybe you run what€™s most like what you€™ve just finished working on so the machine doesn€™t have to be changed. Or you run what can get done the fastest because when you produce more you get paid more.€

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: