Question: Build a Gantt chart based on the following list of tasks and dependencies to build and test a screen form for a new system. Identify
Build a Gantt chart based on the following list of tasks and dependencies to build and test a screen form for a new system. Identify the criticalpath.
.png)
Task ID Description Duration [days Predecessor Start Meet with user Review existing forms 1 ldentify and speci fields Build inial prototype 2 Develop test data valid datal Develop error test data Test prototype Make final refinements
Step by Step Solution
3.48 Rating (155 Votes )
There are 3 Steps involved in it
Task ID Description Duration Precedence 0 Start 0 1 Meet with user 2 0 2 ... View full answer