Carlson Construction Company prepared the following activity times and costs for a building construction project: Required: (1)

Question:

Carlson Construction Company prepared the following activity times and costs for a building construction project:
Carlson Construction Company prepared the following activity times and costs

Required:
(1) Prepare a PERT network diagram for the project, showing times and costs for each activity.
(2) Determine the critical path.
(3) Compute the total cost of the project as planned.
(4) Compute the minimum total cost of completing the project in 12 weeks.