Simmons Company has prepared the following network for a project: Expected time and cost estimates are: Costs

Question:

Simmons Company has prepared the following network for a project:
Simmons Company has prepared the following network for a project:Expected

Expected time and cost estimates are:

Simmons Company has prepared the following network for a project:Expected

Costs for each activity occur uniformly; for example, activity A requires $800 each day.
Required:
(1) Identify the critical path.
(2) Prepare a daily activity and cost schedule.