Complete the following problems: Using the following information, calculate the cost performance index and the schedule performance

Question:

Complete the following problems:
Using the following information, calculate the cost performance index and the schedule performance index. Then calculate the estimate at completion (EAC). Please show calculations for all your answers
Planned value: 6700
Earned value: 6100
Actual costs: 7300
Budget at completion: 38900
Calculate the following values
CPI: _______________________
SPI: ____________________________
EAC: _____________________
Consider the following information:
PV=6500
EV=5000
AC=7200
BAC=32000
Expected Duration=12 weeks
Calculate the following values:
CV __________________
SV __________________
CPI __________________
SPI __________________
EAC __________________
Duration at Completion _______________
Please select the best answer from the following selection to complete each of the questions below related to task dependency.
Start -to-start
Finish-to-start
Start-to-finish
Finish-to-finish
Questions Filling in the name of the appropriate task dependency for each question Task A: Printout a series of computer