Compute and interpret (a) Manufacturing cycle time and (b) Manufacturing cycle efficiency using the following information from

Question:

Compute and interpret
(a) Manufacturing cycle time and
(b) Manufacturing cycle efficiency using the following information from a manufacturing company.
Process time . . . . . . . . . 7.5 hours
Inspection time . . . . . . . 1.0 hours
Move time . . . . . . . . . . . 3.2 hours
Wait time . . . . . . . . . . . 18.3 hours