Question: Concord Construction Inc. agreed to build a new science building on the Northern University campus. Both parties signed the contract on October 31, 2011, for

Concord Construction Inc. agreed to build a new science building on the Northern University campus. Both parties signed the contract on October 31, 2011, for $60 million, which is to be paid as follows:
$5 million at the signing of the contract
$15 million on December 31, 2011
$30 million on December 31, 2012
$10 million at completion, on August 15, 2013
The following costs were incurred by Concord Construction (in millions):
2011…………………….. $ 9.2
2012…………………….. 20.4
2013…………………….. 16.4
Total……………………..$46.0
Required:
a. Calculate the revenue, expenses, and profit (ignoring interest) that Concord Construction should report for each of the three years, using the percentage of completion method.
b. Explain how this method appropriately allows Concord Construction to show the company's performance under the contract.

Step by Step Solution

3.49 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Percentage of completion method b The percentage of completion method should be used to indicat... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

695-B-A-R-R (808).docx

120 KBs Word File

Students Have Also Explored These Related Accounting Questions!