Consider the following data for a project: Activity Time (days) Immediate Predecessor(s) A2 B4 A C5

Question:

Consider the following data for a project: Activity Time (days) Immediate Predecessor(s) A2 — B4 A C5 A D2 B E1 B F 8 B, C G 3 D, E H5 F I4 F J 7 G, H, I 

a. Draw the network diagram. 

b. Calculate the critical path for this project. 

c. How much slack is in each of the activities G, H, and I?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations management processes and supply chain

ISBN: 978-0136065760

9th edition

Authors: Lee J Krajewski, Larry P Ritzman, Manoj K Malhotra

Question Posted: