Ventaz Corp manufactures small windows for back yard sheds. Historically, its demand has ranged from 30 to 50 windows per day with an average of
Ventaz Corp manufactures small windows for back yard sheds. Historically, its demand has ranged from 30 to 50 windows per day with an average of
4646.
Alex is one of the production workers and he works eight hours a day, five days a week. Each order is one window and each window takes
1010
minutes.
What is the cycle time for an order?
A.
100100
minutes per window
B.
1010
minutes per window
C.
125125
minutes per window
D.
500500
minutes per window
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started