Consider the project network diagram shown below. Using this diagram and the activity duration times listed below,
Question:
Activity....................................Duration (days)
A..............................................................4
B.............................................................11
C...............................................................5
D...............................................................3
E................................................................2
F................................................................1
G................................................................4
H................................................................2
I..................................................................3
J.................................................................4
Step by Step Answer:
Project Management A Managerial Approach
ISBN: 978-0470226216
7th Edition
Authors: Jack R. Meredith, Samuel J. Mantel,