Consolidated Edison Co. of New York (Con Ed) sought bids from General Electric Co. (GE) and others

Question:

Consolidated Edison Co. of New York (Con Ed) sought bids from General Electric Co. (GE) and others to supply it with two huge transformers. Con Ed required that the bids be held open for 90 days. GE submitted a written bid and included a clause holding the bid open for 90 days. During that period, Con Ed accepted GE’s bid, but GE refused to honor it. Is there a contract?