Develop an exponential smoothing forecast (a = 0.3) for February 2012 through January 2013. Assume that your
Question:
2013.
MONTH DEMAND
January 2012 119
February............ 72
March............ 113
April............ 82
May............ 82
June............ 131
July............ 111
August ............ 116
September............ 89
October............ 95
November............ 88
December............ 90