Diamond Company produces a chair that requires 5 yards, of material per unit. The standard price of

Question:

Diamond Company produces a chair that requires 5 yards, of material per unit. The standard price of one yard of material is $7.50. During the month, 8,500 chairs were manufactured, using 43,700 yards at a cost of $7.30.

Determine the

(a) Price variance,

(b) Quantity variance,

(c) Cost variance

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer: