Draw a project balance chart for Problem 5. In Problem 5, your company is looking at purchasing
Question:
In Problem 5, your company is looking at purchasing a dump truck at a cost of $65,000. The truck would have a useful life of five years. At the end of the fifth year the salvage value is estimated to be $10,000. The dump truck could be billed out at $55.00 per hour and costs $13.00 per hour to operate. The operator costs $22.00 per hour. Using 1,000 billable hours per year determine the net present value for the purchase of the dump truck using a MARR of 18%. Should your company purchase the dump truck?
Net Present Value
What is NPV? The net present value is an important tool for capital budgeting decision to assess that an investment in a project is worthwhile or not? The net present value of a project is calculated before taking up the investment decision at... Salvage Value
Salvage value is the estimated book value of an asset after depreciation is complete, based on what a company expects to receive in exchange for the asset at the end of its useful life. As such, an asset’s estimated salvage value is an important... MARR
Minimum Acceptable Rate of Return (MARR), or hurdle rate is the minimum rate of return on a project a manager or company is willing to accept before starting a project, given its risk and the opportunity cost of forgoing other...
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Construction accounting and financial management
ISBN: 978-0135017111
2nd Edition
Authors: Steven j. Peterson
Question Posted: