Dreyfus Company has a policy of counting on-hand inventory of one of its products every 45 days.

Question:

Dreyfus Company has a policy of counting on-hand inventory of one of its products every 45 days. When a replenishment order for the product is placed with the supplier, lead time is 8 days. Demand for the product averages 6 units per day with a standard deviation of 1.5 units. It has just been determined that the company currently has 42 units on hand. How many units should the company order if it strives to maintain a 99% service level on this item.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managing Operations Across the Supply Chain

ISBN: 978-0078024030

2nd edition

Authors: Morgan Swink, Steven Melnyk, Bixby Cooper, Janet Hartley

Question Posted: