Each nurse works 8 consecutive hours at the Beaver Medical Center. The center has the following staffing
Question:
Work Period Nurses Needed
1 (7-11)..........................................40
2 (11-3) ..........................................20
3 (3-7)............................................30
4 (7-11)..........................................40
5 (11-3)..........................................20
6 (3-7)............................................10
(a) If y1 represents the number of nurses starting in period 1, y2 the number starting in period 2, and so on, write the linear programming problem that will minimize the total number of nurses needed. (Note that the nurses who begin work in period 6 work periods 6 and 1 for their 8-hour shift.)
(b) Solve the problem in (a).
Use the simplex method, Excel, or some other technology.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Mathematical Applications for the Management Life and Social Sciences
ISBN: 978-1305108042
11th edition
Authors: Ronald J. Harshbarger, James J. Reynolds
Question Posted: