Electric power is to be generated in a hydroelectric power plant that receives water at a rate

Question:

Electric power is to be generated in a hydroelectric power plant that receives water at a rate of 70 m3/s from an elevation of 65 m using a turbine–generator with an efficiency of 85 percent when frictional losses in piping are disregarded the electric power output of this plant, is?
(a) 3.9 MW
(b) 38 MW
(c) 45 MW
(d) 53 MW
(e) 65 MW
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Thermodynamics An Engineering Approach

ISBN: 978-0073398174

8th edition

Authors: Yunus A. Cengel, Michael A. Boles

Question Posted: