Electric power is to be generated by installing a hydraulic turbinegenerator at a site 70 m below

Question:

Electric power is to be generated by installing a hydraulic turbine–generator at a site 70 m below the free surface of a large water reservoir that can supply water at a rate of 1500 kg/s steadily. If the mechanical power output of the turbine is 800 kW and the electric power generation is 750 kW, determine the turbine efficiency and the combined turbine– generator efficiency of this plant. Neglect losses in the pipes.
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Thermodynamics An Engineering Approach

ISBN: 978-0073398174

8th edition

Authors: Yunus A. Cengel, Michael A. Boles