Erwick Construction Company contracted to build a house for Charles. The specifications called for the use of

Question:

Erwick Construction Company contracted to build a house for Charles. The specifications called for the use of Karlene Pipe for all plumbing. Erwick, however, got a better price on Boynton Pipe and substituted the equally good Boynton Pipe for Karlene Pipe. Upon inspection, Charles discovered the change, and he now refuses to make the final payment. The contract price was for $200,000, and the final payment is $20,000. Erwick now brings suit seeking the $20,000. Will Erwick succeed in its claim?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Smith and Roberson Business Law

ISBN: 978-0538473637

15th Edition

Authors: Richard A. Mann, Barry S. Roberts

Question Posted: