Extended Learning Exercise There are two customers requiring three-phase electrical ser-j vice, one existing at location A

Question:

Extended Learning Exercise There are two customers requiring three-phase electrical ser-j vice, one existing at location A and a new customer at location B. The load at location A is known to be 1110 kVA, and at location B it is contracted to be 280 kVA. Both loads are expected to remain constant indefinitely into the future. Already in service at A are three 100-kVA transformers that were installed some years ago when the load was much greater. Thus, the alternatives are as follows:
Alternative A: Install three 100-kVA transformers (new) B now and replace those at A with three 37.5-kVA transformers only when the existing ones must be retired.
Alternative B: Remove the three 100-kVA trans-formers now at A and relocate them to B. Then install three 37.5-kVA transformers (new) at A.
Extended Learning Exercise There are two customers requiring three-phase electrical

Data for both alternatives are provided in Table P9-25. The existing transformers have 10 years of life remaining. Suppose that the before-tax MARR = 8% per year. Recommend which action to follow after calculating an appropriate criterion for comparing these alternatives. List all assumptions necessary and ignore income taxes.

MARR
Minimum Acceptable Rate of Return (MARR), or hurdle rate is the minimum rate of return on a project a manager or company is willing to accept before starting a project, given its risk and the opportunity cost of forgoing other...
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Engineering Economy

ISBN: 978-0132554909

15th edition

Authors: William G. Sullivan, Elin M. Wicks, C. Patrick Koelling

Question Posted: