Find (a) The AOA network and the critical path. (b) All event slacks. (c) Critical path to
Question:
(a) The AOA network and the critical path.
(b) All event slacks.
(c) Critical path to event D.
(d) Critical path probability of completion in 14 days.
(e) The effect if CD slips to 6 days; to 7 days; to 8days.
Transcribed Image Text:
b-9763868017 m-6433205414 a-3103202411 EDEFE
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 52% (17 reviews)
a The critical path is AC CB BE EF b The only event with slack is D at 3 days c If D were t...View the full answer
Answered By
Talha Talib
I am a member of IEEE society. As i am a student of electrical engineering badge 17 but beside of this i am also a tutor in unique academy. I teach calculus, communication skills, mechanics and economics. I am also a home tutor. My student Muhammad Salman Alvi is a brilliant A-level student and he performs very well in academics when i start to teach him. His weak point was mathematics but now he is performing well in mathematics. I am a scholarship holder in Fsc as i scored 1017 marks in metric out of 1100. Later on i got scholarship in Punjab Group of Colleges. I got 2nd position in robotics competition in 2018 as my project home automation select for the exhibition in Expocentre.
4.60+
23+ Reviews
62+ Question Solved
Related Book For
Project Management A Managerial Approach
ISBN: 978-0470226216
7th Edition
Authors: Jack R. Meredith, Samuel J. Mantel,
Question Posted:
Students also viewed these Management Leadership questions
-
Find a, b, c and d if (a) (b) (c) (d) a b b-c 3 1 2 2
-
If the probability that an event E occurs is 3 7, what are the odds that (a) E will occur? (b) E will not occur?
-
C and D are equal partners in the CD partnership. C starts the year with an adjusted basis of $300 in his partnership interest while D starts the year with an adjusted basis of $600. The partnership...
-
Use the Ratio Test to determine the values of x 0 for which each series converges. 00 X' k=0
-
Seneca Co. began year 2016 with 6,500 units of product in its January 1 inventory costing $35 each. It made successive purchases of its product in year 2016 as follows. The company uses a periodic...
-
Susan Spiffy, owner of Spiny Cleaners, drive-through dry cleaners, would like to expand her business from its current location to a chain of cleaners. Revenues at the one location have been...
-
Study the format of the analysis of variances in Exhibit 12-12. Suppose production is 156,000 units. Also assume the following: Other data are as shown in Exhibit 12-12. Prepare an analysis of...
-
A researcher wishes to compare two hotels on the following attributes: Convenience of location Friendly personnel Value for money a. Design a Likert scale to accomplish this task. b. Design a...
-
A matrix A is given along with an iterate X5. 7 2 6,249 A = X5 = -6-1 -6,247 Use these data to approximate a dominant eigenvector whose first component is 1 and a corresponding dominant eigenvalue....
-
Walgreen Company is a well-known drugstore chain. A condensed balance sheet for August 31, 2011, follows ($ in millions): Use a format similar to Exhibit to analyze the following transactions for the...
-
Given the estimated activity times below and the network in Problem 8 above, what is the critical path probability that the project will be completed within: (a) 21 days? (b) 22 days? (c) 25days?...
-
a. Draw the AOA diagram. b. Find the critical path. c. Find the completion time. Activity TE AB .....1 AC .....2 AD .....3 DC .....4 CB .....3 DE .....8 CF .....2 BF .....4 IJ .......2 CE .....6 EF...
-
Walgreens is a drugstore chain operating more than 8,200 stores in 50 states, the District of Columbia, Guam, and Puerto Rico. Walgreens typically builds rather than buys stores, so it can pick prime...
-
The following are situations in which auditors may find themselves. Situations: 1. Spencer is the partner in charge of the audit of Flip Company. He has half in- terest in a joint venture with Flip's...
-
What is the primary rationale for Congress to require mandatory reporting on internal accounting controls?
-
Explain how "privileged communication" differs from confidential information.
-
What is corporate governance and why is it important? What role does the audi- tor play in improving corporate governance?
-
Who is the audit client? Why is it important that the auditor understand who the true audit client is and why that party is the audit client?
-
How do we start with the identification of reputation and its related terms?
-
Determine the values of the given trigonometric functions directly on a calculator. The angles are approximate. tan 0.8035
-
An insurance company in Asia reported profit of $100 million for the financial year through the news-dissemination system of the stock exchange. Its stock price increased several times, as the...
-
Explain how useful each of the following can be during the estimating of project costs: a. Contingency planning and estimating b. Using historical databases c. Usefulness of computer estimating d....
-
On June 12, 2002, Delta Corporation was awarded a $160,000 contract for testing a product. The contract consisted of $143,000 for labor and materials, and the remaining $17,000 was profit. The...
-
Acme Corporation has received a contractual order to build a new tooling machine for Alpha Corporation. The project started several months ago. Table 1514 is the Monthly Cost Summary for June, 2002....
-
Joseph Schumpeter sald that progress occurs through the process of saving and Investment. O True O False
-
The following data are available for the most recent year of operations for Slacker & Sons. The revenue portion of the sales activity variance is $125,000 F. Master budget based on actual sales of...
-
Sanjeev enters into a contract offering variable consideration. The contract pays him $3,000/month for six months of continuous consulting services. In addition, there is a 60% chance the contract...
Study smarter with the SolutionInn App