Firewall Project XT. Using the complexity weighting scheme shown in Exercise 5.3 and the function point complexity

Question:

Firewall Project XT. Using the "complexity weighting" scheme shown in Exercise 5.3 and the function point complexity weighted table shown below, estimate the total function point count. Assume historical data suggest five function points equal one person a month and six people can work on the project.
Firewall Project XT. Using the

a. What is the estimated project duration?
b. If 20 people are available for the project, what is the estimated project duration?
c. If the project must be completed in six months, how many people will be needed for the project?
Exercise 5.3

Firewall Project XT. Using the
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: