Question: For the hyetograph of hourly rainfall values shown in Fig. P6.4, determine the number of events corresponding to minimum inter event time (MITs) of 0,

For the hyetograph of hourly rainfall values shown in Fig. P6.4, determine the number of events corresponding to minimum inter event time (MITs) of 0, 1, 2, 3, 4, and 5 hr. What MIT is needed to have the entire 40-hr sequence treated as one event?

Step by Step Solution

3.40 Rating (162 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

No of events is tabulated blew for various MIT values When MIT 7 the entire rainfall ... View full answer