Question: For the network shown in Figure with all times indicating weeks, answer the following questions: a. What is the impact on the end date of
For the network shown in Figure with all times indicating weeks, answer the following questions:
a. What is the impact on the end date of the project if activity B slips by two weeks?
b. What is the impact on the end date of the project if activity E slips by one week?
c. What is the impact on the end date of the project if activity D slips by two weeks?
d. If the customer offered you a bonus for completing the project in sixteen weeks or less, which activities would you focus on first as part of compression (crashing)analyses?
.png)
START FINISH
Step by Step Solution
3.49 Rating (176 Votes )
There are 3 Steps involved in it
Activity Early Start Early Finish Latest Start ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
93-B-M-L-P-M (842).docx