For the Solved Problem above, assume that the most likely times (m) are the normal activity times

Question:

For the Solved Problem above, assume that the most likely times (m) are the normal activity times and the optimistic times (a) are the activity crash times. Further assume that the activities have the following normal and crash costs:


Activity Costs (Normal Cost, Crash Cost)

1.........($100, 400)

2..........($250, 400)

3.......... ($400, 800)

4.......... ($200, 400)

5. .......... ($150, 300)

6. .......... ($100, 100)

7.......... ($300, 500)


Crash the network the maximum amount possible and indicate the total crash cost.


Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations And Supply Chain Management

ISBN: 289

8th Edition

Authors: Roberta S. Russell, Bernard W. Taylor

Question Posted: