Given the following activities and precedences, draw an AOA or AON diagram: Activity Immediate Predecessor A ..........

Question:

Given the following activities and precedences, draw an AOA or AON diagram:

Activity Immediate Predecessor

A ..........—

B ..........—

C ..........A

D ..........A, B

E ...........A, B

F ..........C

G ........D, F

H ........E, G


Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management A Managerial Approach

ISBN: 978-0470226216

7th Edition

Authors: Jack R. Meredith, Samuel J. Mantel,

Question Posted: