Given the following information about a small project, a. Draw a network diagram. b. Identify the critical

Question:

Given the following information about a small project,

Given the following information about a small project, 
a. Draw

a. Draw a network diagram.
b. Identify the critical path, earliest start and finish and slack for each task.
c. Which of these activities should the project manager track most closely?
d. What would happen if a new estimate for task D increases its expected duration from two days to six days? Would the project take longer? Would anything else change?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managing Operations Across the Supply Chain

ISBN: 978-0078024030

2nd edition

Authors: Morgan Swink, Steven Melnyk, Bixby Cooper, Janet Hartley

Question Posted: