Given the following network (times are in weeks), determine: (a) The ES, LS, EF, and LF for

Question:

Given the following network (times are in weeks), determine:
(a) The ES, LS, EF, and LF for each activity.
(b) The slacks on all activities.
(c) The critical activities andpath.
Given the following network (times are in weeks), determine: (a)