Given the following project (all times are in days): (a) Draw the network and find the critical
Question:
Given the following project (all times are in days):
(a) Draw the network and find the critical path, time, and cost for an all-normal level of project activity.
(b) Calculate the crash cost-per-day (all activities may be partially crashed).
(c) Find the optimal way of getting an 18-day delivery time. What is the project cost?
(d) Find the optimal way of getting a 16-day delivery time. What is the project cost?
(e) Calculate the shortest delivery time for the project.
What is thecost?