Assume that a resource used by activities e, f, g, and h in the figure below is

Question:

Assume that a resource used by activities e, f, g, and h in the figure below is scarce. To which activity would you assign the resource, based on the following rules?

Assume that a resource used by activities e, f, g,

a. Minimum slack
b. Most successors
c. Most critical followers
d. Shortest task first
e. As late aspossible.