Golf Carts Inc. must set up an assembly line for golf carts. Forecasts show that 10 units

Question:

Golf Carts Inc. must set up an assembly line for golf carts. Forecasts show that 10 units per day should be produced. The plant operates one eight-hour shift each day and runs the line continuously during the shifts. The tasks required, task times, and precedence relationships are as follows:

Golf Carts Inc. must set up an assembly line for

a. Draw the precedence diagram.
b. What is the takt time?
c. What is the theoretical number of workstations?
d. Assign the tasks to the workstations to balance the line using the longest operating time rule.
e. What is the efficiency of the balanced line?
f. If demand increased to 12 units per day, what changes would be needed, if any?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managing Operations Across the Supply Chain

ISBN: 978-0078024030

2nd edition

Authors: Morgan Swink, Steven Melnyk, Bixby Cooper, Janet Hartley

Question Posted: