Swoosh Snowboard Company must set up an assembly line for snowboards. Forecasts show that 600 units per

Question:

Swoosh Snowboard Company must set up an assembly line for snowboards. Forecasts show that 600 units per day should be produced. The plant operates two eight-hour shifts each day and runs the line continuously during both shifts. The tasks required, task times, and precedence relationships are as follows:

Swoosh Snowboard Company must set up an assembly line for

a. Draw the precedence diagram.
b. What is the takt time?
c. What are the theoretical number of workstations
d. Assign the tasks to the workstations to balance the line using the longest operating time rule.
e. What is the efficiency of the balanced line?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managing Operations Across the Supply Chain

ISBN: 978-0078024030

2nd edition

Authors: Morgan Swink, Steven Melnyk, Bixby Cooper, Janet Hartley

Question Posted: