Swoosh Snowboard Company must set up an assembly line for snowboards. Forecasts show that 600 units per
Question:
Swoosh Snowboard Company must set up an assembly line for snowboards. Forecasts show that 600 units per day should be produced. The plant operates two eight-hour shifts each day and runs the line continuously during both shifts. The tasks required, task times, and precedence relationships are as follows:
a. Draw the precedence diagram.
b. What is the takt time?
c. What are the theoretical number of workstations
d. Assign the tasks to the workstations to balance the line using the longest operating time rule.
e. What is the efficiency of the balanced line?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Managing Operations Across the Supply Chain
ISBN: 978-0078024030
2nd edition
Authors: Morgan Swink, Steven Melnyk, Bixby Cooper, Janet Hartley
Question Posted: