Hidalgo Company manufactures goods to special order and uses a job order cost system. During its first
Question:
a. Materials purchased on account . . . . . . . . . . . . . . . . . . . . . . . . . . . . $37,000
b. Materials issued to the factory:
Job 101 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 2,200
Job 102 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5,700
Job 103 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7,100
Job 104 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1,700
For general use in the factory . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1,350
c. Factory wages and salaries earned:
Job 101 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 2,700
Job 102 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6,800
Job 103 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9,200
Job 104 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2,100
For general work in the factory . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2,250
d. Miscellaneous factory overhead costs on account . . . . . . . . . . . . . . . $ 2,400
e. Depreciation of $2,000 on the factory machinery recorded.
f. Factory overhead allocated as follows:
Job 101 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 1,200
Job 102 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2,000
Job 103 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3,800
Job 104 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1,000
g. Jobs 101, 102, and 103 completed.
h. Jobs 101 and 102 shipped to the customer and billed at $39,000.
Required:
1. Prepare a schedule reflecting the cost of each of the four jobs.
2. Prepare journal entries to record the transactions.
3. Compute the ending balance in Work in Process.
4. Compute the ending balance in Finished Goods.