If the indirect costs for each duration are $300 for 27 weeks, $240 for 26 weeks, $180
Question:
If the indirect costs for each duration are $300 for 27 weeks, $240 for 26 weeks, $180 for 25 weeks, $120 for 24 weeks, $60 for 23 weeks, and $50 for 22 weeks, compute the direct, indirect and total costs for each duration. What is the optimum cost-time schedule? The customer offers you $10 for every week you shorten the project from your original network. Would you take it? If so for how manyweeks?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project management the managerial process
ISBN: 978-0073403342
5th edition
Authors: Eric W Larson, Clifford F. Gray
Question Posted: