In 2005, the average cost to construct a 150,000-barrel-a-day oil refinery was $2.4 billion (excluding any interest

Question:

In 2005, the average cost to construct a 150,000-barrel-a-day oil refinery was $2.4 billion (excluding any interest payments). This capital invest-ment is spread uniformly over a five-year construction cycle (i.e., the refinery starts producing products in 2010). Assume end-of-year cash-flow convention and answer the following questions. (Chapter 3 and 8.2)
a. If the cost of capital spent to build the refinery is 10% per year, how much interest will be charged (as a lump sum in 2010) during the construction of this project?
b. If the cost-capacity factor is 0.91, what is the approximate cost to build a 200,000-barrel-a-day refinery in 2005?
c. If inflation of the construction cost of a refinery is 9.2% per year, what is the estimated cost of building a 200,000-barrel-a-day refinery in 2015?
Cost Of Capital
Cost of capital refers to the opportunity cost of making a specific investment . Cost of capital (COC) is the rate of return that a firm must earn on its project investments to maintain its market value and attract funds. COC is the required rate of...
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Engineering Economy

ISBN: 978-0132554909

15th edition

Authors: William G. Sullivan, Elin M. Wicks, C. Patrick Koelling